The Lagos
State Government has earmarked N120 billion of the N844 billion for the
construction of 4th Mainland Bridge on relocation of service, contingency,
design/supervise and land acquisition and compensation to owners of property
expected to give way for the project.
This was
contained in a presentation obtained by Vanguard, which clarified financial
commitment on the project.
The State
Government had in April revealed that with the new alignment adopted for the
project, 800 structures and shanties would be affected by the construction of
the 38 kilometre road.
The document
stated that the total length of the Bridge was 38 kilometre, stating that 25
kilometre of the Bridge would fall on the Mainland axis of the state, eight
kilometres on the lagoon and five kilometres will be on the Lekki corridor.
According to
the presentation; “N20 billion would be spent on land acquisition and
compensation to owners of property on the route adopted for the 4th Mainland
Bridge. “N17 billion would be expended on relocation of service and N67 billion
earmarked for contingency” that may arise during the construction of the
project. “N16 billion of the total fund for the project would be expended on
design/ supervising of the project,” the presentation added.
It further
gave a breakdown of the N844 billion, noting that the initial cost of the
project, that is, to get it operational between year 2016 and year 2021, was
N790 billion.
The project
will be constructed under a Build, Operate and Transfer, BOT concession and the
state’s Public-Private Partnership, PPP programme for a period of 40 years. The
presentation stated that during the concession period (2021 and 2061), N20
billion would be spent on annual operating cost while N5 billion for the
“structural pavement” repair works between 2018 and 2033.
Also, the
presentation disclosed that N19 billion was earmarked for the five year refresh
programme of work along the route between year 2030 and 2061 while N10 billion
would be spent on the ‘Add overlay plus line and refurbish before handback’
between year 2055 and year 2061.
The
presentation noted that due to the state of the project, “it cannot be
constructed in phases because it would cost more than expected.”